Doesn’t it bug you that you always estimate development time lower than the time you actually spend on development? And you never seem to learn? Many try to find the answer in psychology, this may hold some truth, but a large portion of this bias can easily be explained mathematically. The problem is, that we foolishly assume normal distributions, where they simply cannot be.

The wrong assumption

Let’s start with a simple example. We have a rough idea that our task is going to take 6 hours to develop (e.g. a non-trivial UI component along with backend endpoint calls and some styling). Because software development is software development, we take into account the possibility of a high deviation from this mean, say +/- 4 hours. We assume that we are confident with our estimated mean and that in sum, overestimated and underestimated tasks will cancel each other out. And that’s where our intuition is terribly wrong!

If we assume a +/- to be reasonable the same amount to both sides of the estimate, we implicitly assume a normal distribution (with mean 6) as shown in the following graphic:

Expected Distribution

However, all time durations below zero cannot exist by definition. You cannot win time with a task, you can just spend more or less of it.

Deviation from an average estimate can never be normally distributed because it cannot go below zero. That’s why in aggregate, our estimates are systematically wrong to the left.

Hence, to correct our assumption to a more realistic (probably still wrong) distribution, we cancel out the red area below:

Impossible Cases

But with this cut, our estimated mean is not the expected mean of the distribution anymore. Basically we have to shift it to the right as far as it can fit the red surface between its old and new position. This corresponds to the integral under the probability density function.

You can see the correction in orange color below:

Deviation from Estimate

So by how much is our 6 (+/- 4) hours estimation off? In that case, 13.5% off. Systematically.

How does this correspond to reality?

So far we have stayed rather theoretical. But the bias pointed out above does correspond to the real world. Let’s think a bit more about our +/- 4 hours. We know this is a reasonable range because with experience, we have learned that at least 2 in 3 times we have developed similar things in the past, we have been within this range. So far, normal distribution applies, we are within the standard deviation and the 66% percentile. And we never go below zero. But we have forgotten the long tail, far to the right of the distribution.

The long tail is the one time we spent 17 hours on such a task, because requirements changed the minute before completion. That’s not a frequent case, and we tend to think we can ignore it.

But that would be fatal: Our assumption that the pluses and minuses cancel each other out cannot work anymore. Because we cannot cancel 6 + 11 out to the left, only 6 - 6 is remotely possible. We would need to overcompensate and complete two tasks estimated at six hours in 30 minutes each! The long tail is responsible for moving only a few tasks to the right on the time axis, but far to the right. And that is why even seasoned developers tend to estimate too low in aggregate. They can well be 10% off or more, the higher the variance.